Archaeologists at Powick Old Bridge found a 15th or 16th century signet ring, a fired musket shot and an 1899 ha'penny. Repairs start in spring 2027 and the bridge should reopen in 2028.

A merchant’s signet ring from the late 15th or 16th century has been found in the river mud beneath Powick Old Bridge, the closed medieval crossing over the River Teme on the south-western edge of Worcester. Archaeologists working ahead of the bridge’s repair also found a musket shot that had been fired and a Victorian ha’penny. Worcestershire County Council announced the finds on 13 November.

The bridge has been shut to walkers and cyclists since February 2024, when part of a supporting wing wall collapsed into the Teme. The council’s project page now says it expects the bridge to reopen during 2028.

Overview

Updated 23 November: the county council said on 20 November that this phase of work is on schedule to finish by mid-December, subject to weather and river levels. More than 227 one-tonne bags of stone have been placed to backfill the dig, with 32 more to come, and the stone will be reused in the permanent repair. The contractor returns in spring 2027 (Worcestershire County Council).

  • What was found: a copper alloy signet ring from the late 15th or 16th century, a lead musket shot flattened by impact, and a Queen Victoria ha’penny dated 1899.
  • Why it matters: the bridge stands close to the site of the 1642 skirmish at Powick Bridge and the 1651 Battle of Worcester.
  • When it reopens: permanent repairs are due to start in spring 2027, with reopening expected in 2028, subject to approvals.
  • Budget: the council says funding is secured, taking the project budget to £6.336m.

The three finds

The ring is the most significant find, according to the council. It was recovered from river silts immediately downstream of the bridge. It carries a reversed letter “R” and would have been pressed into wax to seal letters and documents. The council believes it was worn by a merchant.

A lead musket shot, flattened on one side, photographed beside a five centimetre scale bar
The lead musket shot found below the road surface at Powick Old Bridge. Photo: supplied by Worcestershire County Council

The musket shot is not fully round. It is squashed on one side, which shows it was fired and hit something solid. It came from layers of gravel and river silt below the present road surface.

The council’s news release links the area to the skirmish at Powick Bridge in 1642, regarded as the opening clash of the English Civil War, and to the Battle of Worcester in 1651. It also says it has not been possible to confirm whether the shot is connected to either event.

The ha’penny was found inside the brick parapet wall on the downstream side of the bridge. That wall was rebuilt in the early 20th century after an earlier stone wall partly collapsed and washed out. The coin is thought to date from that rebuild.

Councillor Tom Wells, the county council’s cabinet member for highways and transport, said: “These discoveries remind us that Powick Old Bridge is far more than a piece of infrastructure. It is a nationally important historic structure that has witnessed centuries of local and national history.”

Why the repair is taking so long

Powick Old Bridge is Grade I listed and a Scheduled Ancient Monument. Historic England says it was built before 1447 and partly rebuilt in the 17th century, according to the council’s project page. It is about 60 metres long and up to 7 metres wide.

The page says the collapse was likely caused by flooding and a build-up of debris. Any repair needs Historic England’s approval, a flood risk permit and Natural England permissions.

Work already finished, according to the council:

  • recovery and storage of the original bridge materials
  • a temporary support structure holding up the bridge
  • foundation strengthening and piling
  • choice of the permanent repair method, with approval in principle from the technical approval authority

The timetable the council now gives:

When What happens
By the end of 2026 Detailed design finished and approved by Historic England; remaining consents submitted
Early 2027 Severn Trent utility work; contractor appointed; site set up
Spring 2027 Permanent repairs start, rebuilding the damaged abutment and repairing the masonry arch
2027 to 2028 Repairs carried out; temporary support removed; testing and final approvals
2028 Bridge expected to reopen

The council says the 2028 date depends on approvals and utility work arriving on time, and on there being no setbacks such as flooding.

What it means for you

The old bridge stays closed to walkers and cyclists until the repair is finished, which the council expects to be some time in 2028.

The council posts progress updates on its Powick Old Bridge page. The next milestone to watch is Historic England’s approval of the design, due by the end of this year.